Bitfarms Ltd. (NASDAQ:BITF) Q4 2025 Earnings Call Transcript

Bitfarms Ltd. (NASDAQ:BITF) Q4 2025 Earnings Call Transcript March 31, 2026

Operator: Good day, and welcome to the Bitfarms Fiscal 2025 Conference Call. [Operator Instructions] Please note, this call is being recorded. I would like to turn the call over to Jennifer Drew-Bear from Bitfarms Investor Relations. Please go ahead.

Jennifer Drew-Bear: Thank you, and welcome to Bitfarms Fiscal Year 2025 Conference Call. With me on the call today are Ben Gagnon, Chief Executive Officer and Director; and Jonathan Mir, Chief Financial Officer. Before we begin, please note this call is being webcast with an accompanying slide presentation. Today’s press release and our presentation can be accessed on our website under the Investors section. Turning to Slide 2. I’d like to remind everyone that certain forward-looking statements will be made during the call, and that future results could differ from those implied in this statement. The forward-looking information is based on certain assumptions and is subject to risks and uncertainties. And I invite you to consult Bitfarms 10-K for a complete list.

Also, please note that references will be made to certain non-GAAP financial measures, and therefore, may not be comparable to similar measures presented by other companies. We invite listeners to refer to today’s press release and our 10-K for definitions of the aforementioned non-GAAP measures and their reconciliations to GAAP measures. Please note that all financial references are denominated in U.S. dollars, unless always noted. And now turning to Slide 3. It is my pleasure to turn over the call to Ben Gagnon, Director and Chief Executive Officer. Ben, the floor is yours.

Ben Gagnon: Good morning, everyone, and welcome to our fiscal year 2025 earnings call. In 2025, we made a bold decision to walk away from our legacy business, Bitcoin, and build the infrastructure in North America for what comes next, HPC and AI. It was a year of deliberate and consequential transformation with a clear mandate. Secure North American pipeline, strengthen our balance sheet, accelerate site development, and position ourselves to engage customers from a place of operational momentum at the peak of the energy bottleneck constraining the growth of AI. I can say with confidence and pride that we accomplished exactly what we set out to do. The foundation you see today, the capital structure, the sites, the team, the strategy was engineered through deliberate choices, developed with discipline and built to propel us forward.

We made foundational changes to reposition the business and made 100% of our focus on North American HPC infrastructure development. No half measures, no compromises and in time, no Bitcoin. We built a new company. And while we are presenting as Bitfarms today, tomorrow marks our beginning as Keel infrastructure. The name says it all. A Keel is the bottom of structural component of a vessel. It’s what keeps it stable and moving forward in the right direction regardless of the condition above the water line. It is structural, it is essential, and it is exactly how we see our role in the HPC and infrastructure landscape. We are not here to compete with hyperscalers or neoclouds. We are here to enable them. Our focus is providing the critical and largely invisible foundation that will allow the world’s most advanced AI platform to deploy on time and scale without interruption.

We expect to close the re-domiciliation and finalize our rebranding efforts tomorrow, April 1, and we’ll begin trading under the ticker KEEL, 2 business days after completion of the transaction on the Nasdaq and the TSX. We are entering this new phase from a position of strength. With over 2 gigawatts in our pipeline, Keel is a regional leader with some of the largest power land portfolios in some of the highest demand markets in North America and with robust financial strength to execute against our plan. Our current liquidity is far in excess of the CapEx budgeted to get us through permitting and ultimately to start signing leases, giving the company significant financial flexibility to execute on our strategy. And our strategy is equally as clear.

We are designing all of our site and campus developments as either powered shell or co-location facilities. We believe this is where we can deliver the most value to shareholders and serve our potential customers at the speed and to the specifications they need. We were originally exploring in parallel to co-location the potential benefits of pursuing a small amount of GPU as a service at our Washington site, Moses Lake, where due to the lowest cost power for data centers in the country and a relatively smaller footprint, we believe it could be an avenue to drive additional shareholder value. Since our last quarterly call, we have spoken with an increased volume of potential customers. And it’s clear from those conversations, the most accretive business model for the site is one of co-location.

This is not specific to Moses Lake and applies to all of our other sites as well, where demand is even higher. So we will focus on what we do best, being an infrastructure developer and owner. This plays directly to our core competencies. We are a team of developers united by disciplined action, building cost-effective institutional-grade infrastructure at the pace our customers require. The same capabilities have built our energy platform, speed to market, capital discipline, operational rigor precisely what HPC and AI deployments demand today. This is just the natural extension of what we do best. So with all the pieces in place and with the overwhelming support of our shareholders who voted over 99% in favor of the HPC and AI pivot, the U.S. redomicile and the rebrand.

Starting tomorrow, we are Keel infrastructure. Turning to Slide 4. When we sat on our pivot, we developed a 3-year transformation plan, one that as of today, we are nearly halfway through completing. In 2025, we did the intensive foundational work for our transformation, including the Stronghold acquisition, securing more power in Pennsylvania, rebalancing the portfolio to North America, a $588 million raise fully institutional and oversubscribed, our U.S. GAAP transition, New York headquarters and establishing a new executive team. This work is done. With power and land secured in some of the power markets that matter most, a team of internal experts and strategic partners that have built data centers for the largest companies in the world and a balance sheet engineered to see us through 2026, we are well positioned to continue our site development and deliver against the time lines, our prospective hyperscalers and neocloud customers need.

2026 is all about execution. Effective tomorrow, we will have completed our redomiciliation to the United States and officially rebranded as Keel infrastructure. Two major milestones that position the company for the next phase of growth. With that complete, we expect the next significant milestones to come from executing against our development at Panther Creek, Sharon and Moses Lake, where we are moving full steam ahead and working diligently across three simultaneous and active work streams. One, finalizing permits, which we expect to be done in the coming months. Two, continued work on architecture and engineering in line with ongoing customer conversations and requirements. And of course, three, our go-to-market to secure highly financeable leases with investment-grade tenants.

Commercialization is well underway. The upcoming milestones investors can expect are completion of preconstruction activities like permitting, progress in customer engagement and ultimately lease execution, which we are confident we can achieve this year and will be major catalysts. 2026 is also the year where we expect to leave Bitcoin and Bitcoin mining behind. While we were probably one of the first miners to commence wind down of our Bitcoin mining exposure to reinvest that capital into infrastructure for HPC and AI, we will be accelerating those efforts in 2026 as site developments progress. 2027 is all about delivery. This is the year when we anticipate that sites would come online, we’d begin delivering megawatts to customers, HPC and AI revenue really begins and we complete our transition to a premier North American HPC and AI infrastructure company.

By the end of 2027, we expect Keel will be a proven infrastructure developer and a regional leader across Pennsylvania, Washington and Quebec, and we will just continue to grow and scale from there in 2028 and beyond to over 2 gigawatts as we execute against our expansion capacity. Turning to Slide 5. In HPC infrastructure, power, location and time lines are everything. We hold something scarce and valuable secured power, land and expansion capacity in Pennsylvania, Washington State and Quebec. Some of the most in-demand markets with some of the biggest barriers to entry. We know it and so do our potential tenants. Our campuses offer solutions to hyperscalers and neocloud’s greatest scaling problems, location, proximity and fiber connectivity to major metro areas and data center clusters solving for latency issues and giving our tenants proximity to their own customers and other data centers.

Time lines. Our robust secured power for ’26, ’27 and with expansion capacity in 2028 is highly coveted in an environment where energy capacity is hard to find and multiyear waitlists are the norms. We create value for tenants by enabling them to deploy years earlier by leasing from us rather than to invest in growing organically. An energy-efficient cool climate, the lower the PUE, the more critical megawatts. Panther Creek is a great example of seeing the hyperscaler and neocloud’s appetite at play. While there is a lot of interest in the site last year, inbound customer activity surged after we secured zoning in February. This is not a coincidence. It is the proof point and one that we’ve been making for the last year, but may still be confusing to some investors.

So we’d like to be clear that investment-grade tenants value derisk sites where they can move from lease to revenue fast. The more we advance, the better our leverage. The better our leverage, the better the leases, and the more long-term value we create for shareholders. Turning to Slide 6. It is indisputable that power is the binding constraint for AI infrastructure deployment and will remain so for the coming years. Leading investment banks, Goldman Sachs, JPMorgan, Wells Fargo, Guggenheim, Moelis, they’ve all published extensively on this. And the consensus is clear. New power generation cannot come online fast enough to meet AI demand today, tomorrow or in the next 5 years. This bottleneck is structural, not cyclical. Hyperscalers and neoclouds that used to plan on 12-month horizons are now locking in 24- to 36-month supply chain commitments.

Not tied to specific projects, but as platform level agreements and are now actively competing for the power and land to deploy it. While you are probably familiar with this information, here you can see a summary of the five development sites. The power we have secured and in some cases, the incremental power opportunities that make up our 2.2 gigawatt pipeline. Turning to Slide 7. I want to take a moment to put our current valuation context because there is a meaningful disconnect between where we trade today and the value we are positioned to capture as a company. When we analyze our current valuation against our peers, the picture becomes clear, at approximately $1.9 million per available megawatt of secure 2027 capacity, we’re trading in the middle of a Bitcoin miner Group, valued at roughly $1.7 million to $2.1 million for 2027 megawatt meaning we are being valued based on having power but not what we are doing with it.

For shareholders and bondholders, we see three distinct catalysts, each capable of driving meaningful reratings. The first is obviously lease execution. Across our sector, companies that have signed leases trade at $4 million to $6 million per 27 megawatts, a 2 to 3x premium to where we are today. This is the market’s consistent signal driven entirely by lease execution, not facility delivery, not revenue generation, just signed leases. A signed lease secures revenue and financing derisking the developments. The market pays for that with nearly 500 megawatts actively being commercialized today and visibility on permitting across Panther Creek, Sharon and Moses lake, this catalyst is well within reach. The second catalyst and arguably the most powerful for long-term holders is securing our expansion capacity.

A bustling server farm, reflecting the company's investment into cryptocurrency mining.

2/3 of our 2.2 gigawatt portfolio or approximately 1.5 gigawatts is expansion capacity, which we believe the market is assigning little to no value. While securing these megawatts is a process that will take more time, we believe additional megawatts can be secured in the second half of 2026 requiring very little CapEx while representing significant embedded value as powered land even before a lease is signed or there is a shovel in the ground. The third catalyst is delivering in 2027. Once facilities are derisked through commissioning and begin generating revenue under long-term contracts, the development risk should drop dramatically and the operator valuation numbers become transformational yet again. We are not taking a leap of faith on technology, our ability to see our power or market demand.

The tech is here. The power is secured, the sites are advancing, the inbound demand is real, but the market has not yet priced in is the transformation that happens when a developer becomes a counterparty when we move from site advancing to lease executing. This is the main opportunity ahead of us to accelerate permitting, execute leases, secure our expansion capacity and ultimately deliver to our customers. This is how we will create value for our shareholders and bondholders. Turning to Slide 8. Our execution plan is defined by six areas, each supporting our ability to deliver at the pace and scale our future customers require. First, we’ve secured our deep bench of talent by adding over 60 years of infrastructure and development in over 50 years of data center construction experience combined in just the past few months.

People have delivered at scale for the most demanding customers in the world. Jonathan Mir joined as CFO, bringing 25 years of energy infrastructure strategy and project finance expertise. We have also added an SVP of construction and of power, a VP of HPC Operations and Head of permitting to oversee the execution of these critical functions. We’ve assembled the right team to execute on our vision. Second, we are engaging the right industry leaders as partners, T5, Turner Construction, Corgan, [ WWT ], Vertiv. These firms have built data centers for the world’s largest hyperscalers not once but hundreds of times. When customers look at our project partners, which will be available on the new website when it launches tomorrow, they will see that we have also assembled the right partners to ensure better outcomes.

Third, we have the capital required to bring our sites to market. As of March 27, 2026, our liquidity stands at $520 million in cash and Bitcoin, which we expect is much more than the CapEx budgeted to get us to a lease at Panther Creek, Sharon and Washington. Jonathan will go into more detail on our capital position and financing strategy shortly, but the headline is simple. We’re well funded and can move fast. Fourth, a disciplined Bitcoin exit. It is clear we are no longer a Bitcoin miner. However, with strong, robust liquidity, we can have a disciplined approach to our exit strategy. We will continue to operate up until the time sites need to be prepared for construction maximizing free cash flow before selling the miners. We will also opportunistically sell Bitcoin into strength to capture and reinvest every dollar we can into HPC and AI infrastructure.

Fifth, power assets that cannot be replicated. Our megawatts sit in regions with large barriers to entry, Pennsylvania, Washington State and Quebec, all have multiple year waitlists. No one is cutting the line. Our 350 megawatts at Panther Creek, 110 megawatts at Sharon and 18 megawatts in Washington were secured before the AI demand wave made these markets highly coveted. This isn’t power others can easily replicate giving us competitive edge with high-quality tenants to understand these markets and are hungry for assets like ours, which leads us to our sixth point. In this market, speed to power is what drives value. For our customers, the opportunity cost of delayed deployment is huge. So the priority is getting capacity online as quickly as possible.

Every day of delay is lost revenue. As a result, power availability and certainty of delivery are the primary drivers of lease economics. This dynamic has pushed lease rates higher since our Q3 call, exactly as we said it would. The opportunity in front of Keel infrastructure is real. We now have the assets and the team is ready. I’m so proud of what we built in 2025, and I’m confident in what we’ll deliver in 2026 and 2027. With that, I’ll turn the call over to Jonathan.

Jonathan Mir: Thanks, Ben. Turning to Slide 9. I joined the team 5 months ago. My focus has been on sharpening our approach to capital allocation, strengthening our balance sheet and capital structure and ensuring the financing actions support long-term shareholder value creation. I’ve had a front row of the depth of talent, the operational discipline and the strategic momentum across Bitfarms. I work closely with our operations and development teams both to understand the current trajectory of our assets and to ensure our capital plans are aligned with the opportunities ahead. What stood out to me is the extraordinary potential we have driven by the quality and potential of our sites, a strong balance sheet, the best liquidity position in the company’s history and a broad team that’s both deeply engaged and committed to excellence.

We’re moving quickly and with purpose. I’m pleased to be here with you today and discuss the progress we’re making. I’ll use this time to walk through our performance for fiscal year 2025 and outline our current capital strategy that we believe supports the accretive growth we’re targeting for 2026 and beyond. Turning to Slide 10. Before discussing our financials for the quarter, I want to briefly frame the results are presented this quarter. As of Q3 2025, the Paso Pe facility in Paraguay has been classified as held for sale. As a result, all revenues, operating costs and asset balances associated with Paso Pe are treated as discontinued operations in our fiscal year 2025 financials. So when I refer to continuing operations, I am speaking exclusively about our North American platform, the foundation of our transition into HPC and AI infrastructure.

With that, revenue for fiscal year 2025 was $229 million, up 72% year-over-year. Operating loss for fiscal year 2025 was $150 million including noncash depreciation of $98 million and $28 million of impairment charges. This compares to an operating loss of $28 million in 2024, which included $102 million of noncash depreciation and $4 million of impairment charges. Net loss for 2025 was $209 million or a $0.38 loss per basic and diluted share compared to a 2024 net loss of $7 million or $0.02 loss per basic and diluted share. The differences between 2024 and 2025 were driven by a number of factors, including change in fair market value of digital assets, primarily due to the decline of Bitcoin prices and realization of gains on disposal of Bitcoin during the year.

Two additional items also impacted year-over-year comparability. First, we saw a loss of $68 million, reflecting changes in our derivative assets and liabilities. Second, 2025 impairment charges were $25 million higher than in 2024. For the year, our adjusted EBITDA was $29 million compared to $31 million in 2024. Turning to Slide 11. 2025 was a deliberate year of balance sheet optimization and improvement, providing the foundation for our next phase of growth. We successfully issued an oversubscribed $588 million convertible offering, significantly expanding our liquidity. And in February, we repaid the Macquarie debt facility eliminating legacy debt, simplifying our capital structure and freeing the company from covenants. Each of these supports the pursuit of our HPC infrastructure strategy.

The Macquarie facility had been originally used to accelerate development at Panther Creek, funding critical project activities, including long lead time item procurement and substation work. Retiring the facility was a strategic decision, strengthens the balance sheet and gives us the flexibility to secure a more cost-effective financing at either the parent or project level. Our current cash position of $520 million provides the runway to advance Panther Creek, Sharon and Moses Lake through lease execution without accessing capital markets. Though we may do so if attractive opportunities arise that improve our ability to deliver the best possible long-term risk-adjusted shareholder returns. Macquarie was an excellent partner, and we appreciate their support so early in our pivot to HPC AI infrastructure.

Turning to Slide 12. As we pivot to commercialization of our development sites, we have a clear financial strategy based on three principles. Capital allocation, capital formation and capital structure. Taken together, they are designed to deliver the best possible long-term risk-adjusted shareholder returns. First, capital allocation. We deploy capital into projects where the earnings potential exceeds their weighted average cost of capital. We rotate capital from businesses that are noncore or earning less than optimal returns and deploy the capital into higher return investments. Second, capital formation. Our financing strategy is designed to fund our very large growth opportunities while maintaining the liquidity needed for a stable base of operations.

We will be opportunistic in our financing execution. We will fund construction of our data center projects using project or parent level bet and project or parent level equity or equity-linked offerings. We’re taking a disciplined approach and at this time, are well capitalized to actively commercialize and execute leases across Panther Creek, Sharon and Washington. Third, capital structure. Our capital structure is designed to capture the best possible long-term risk-adjusted shareholder returns while also retaining overall corporate flexibility and support growth. Our objective is to operate with a deliberate liquidity strategy in order to enable clear-headed commercial decisions and capital allocation decisions rather than having liquidity drive time lines.

Stepping back, our road map is clear. We are building a regionally focused high-growth HPC AI infrastructure platform, grounded in disciplined capital allocation, a strengthened balance sheet and a development cadence that maximizes returns and minimizes risk. We’re funded through the key derisking stages, permitting and leasing across Moses Lake, Sharon and Panther Creek and we’re entering 2026 with momentum, optionality and a balance sheet engineered for growth. We have the right people, assets, liquidity and strategy and we’re well positioned to capture for our shareholders the long-term value potential we have today. With that, I’d like to return the call to Ben for closing remarks.

Ben Gagnon: Thanks, Jonathan. A little over a year ago, as our team began actively integrating AI into both our business and our daily lives, we came to a realization. This isn’t just another technology cycle. It’s a paradigm shift. More comparable to the industrial revolution than the Internet revolution. The fundamental measure, productivity capacity is no longer calories or joules, but tokens. This became strikingly clear 2 weeks ago at NVIDIA GTC, where I witnessed hundreds of companies applying AI to everything from straightforward tasks by cleaning and image generation to extraordinary complex applications, including protein folding, cystic simulations and even brain surgery. Walking the conference floor, speaking to the attendees, one thing was unmistakable.

We’ve only begun to scratch the surface of AI’s potential. Yet even in these early days, AI is already empowering individuals, communities and companies to accomplish exponentially more. We’re witnessing Jevons Paradox unfold simultaneously across every industry, thanks to AI, where improved efficiency can paradoxically drive higher, not lower demand. It is literally never cost less to transform an idea into an action, a product, an image, a refined concept, a service or countless other outlets. The possibilities are truly limitless, and while no one can predict exactly how AI will reshape our future, uncertainty remains. It will require enormous amounts of power. Our 2.2 gigawatts of capacity and strategically position land across Pennsylvania, Washington and Quebec sit directly in the path of this transformation, and we intend to capitalize on that opportunity for our shareholders.

We look forward to the opportunities ahead. With that, I would like to open the call to Q&A. Operator, please go ahead.

Q&A Session

Follow Bitfarms Ltd. (NASDAQ:BITF)

Operator: [Operator Instructions] And our first question comes from Mike Grondahl with Northland.

Mike Grondahl: First question, Ben, you talked about your decision not to go the GPU rental route at Moses Creek. And just the colocation route, could you talk a little about what a couple of the major drivers were that got you to that decision?

Ben Gagnon: Yes, it’s a great question, Mike. When we first started talking about in Q3, we were always evaluating this alongside with the colocation. We’re trying to maximize the value for shareholders. So we’re always going to evaluate multiple different business models at our sites. And because they have the lowest cost energy and all these other benefits, we thought it would make a lot of sense. But as we’ve continued to have increasing amounts of customer conversations for Washington and other sites. It was just really clear to us that the best opportunity for us is to just remain a pure-play infrastructure developer and owner and let these customers who really want these megawatts lease these megawatts.

Mike Grondahl: Got it. Got it. And then maybe secondly, you articulated, I’ll say, a philosophy a quarter or 2 ago about waiting and waiting on signing a lease as terms were continuing to improve kind of implying you’re going to be really patient and wait on a lease. Could you kind of update how you’re thinking about that lease execution strategy and the potential timing around it?

Ben Gagnon: Yes. Our strategy on lease execution has been consistent. It remains consistent today. Our view is that the best way to maximize value for shareholders is to get the best terms in a lease because that’s going to be what is going to be driving our NOI and our multiple. And so when we’re looking to sign 10- to 15-year agreements, it’s really important for us to take the — maybe a little bit more time than investors may want us to in order to get better terms for longer. When it looks at what is really driving the value in these lease economics, one of the biggest elements is risk, and we’ve spoken to this multiple times over the last couple of months. And the biggest risk for most of the people — to go out there and have conversations and get a lot of interest.

And in some cases, you could even sign a lease prior to getting permits. But all of that risk is going to be priced into the agreement, you’re going to be locked into it for 10 to 15 years, and that’s going to negatively impact the long-term value that we’re creating for shareholders. So our strategy has been incredibly consistent. And the benefit for us is that we are operating in high demand markets with high barrier to entry. So it takes a little bit longer to get permits going in Pennsylvania or in Washington than it does in Texas, which is the easiest market in the United States for that. But we believe that drives a lot of extra value because it’s way more scarce, it’s way harder to acquire and there’s just not as much optionality.

Operator: Our next question comes from Brett Knoblauch with Cantor Fitzgerald.

Brett Knoblauch: Maybe to start, could you maybe just go into detail on what permits at what sites you guys are waiting to receive?

Ben Gagnon: So permits is a complicated process, and we are develop — we’re getting permits across multiple sites in multiple jurisdictions. So they all have different rules, different regulations, different time lines, different reviews, different authorities. So it’s far too much detail to get into exactly what permits are remaining on all the different sites. But we are continuing to make good progress and kind of — we’re looking at the visibility over the next couple of months. And with what we’ve had so far with the community engagement success that we’ve had so far, we think that in the coming months, sometime around the mid- to late summer time. we should be achieving the full permitted status across at least one, if not all of the sites.

Brett Knoblauch: And then maybe just on the leasing environment across the different sites that you guys have. I guess we were under the impression that maybe Sharon would be first to go given it’s relatively further along. Is that still how you guys are thinking about it? And then in the presentation when you guys kind of list the power pipeline and road map. How much of that is from generation on site that you guys are looking into? And do you have any update on where you guys are with respect to sourcing that generation?

Ben Gagnon: Yes, sure. So the — to answer the second part of your question first, all the power that we’re talking about developing for our HPC and AI data centers right now is grid connected. So the two operating power plants that we have at Scrubgrass and Panther Creek. Currently, that math is not in those charts for the secured capacity or the site development plans. But in Scrubgrass particular, we are working to expand the generation capacity there with natural gas. So we’ve been working to tap into the Tennessee Natural Gas Pipeline. We’re achieving pretty good results there with the engineering firms. There’s still probably another month or two to go before we’re getting a clear path forward on the engineering plans.

But Scrubgrass is our more of our pipeline site. And so those — that power generation opportunity is more of a 2028 and 2029 time line. Everything else is grid connected, it’s secure today or it’s currently active. And sorry, Brett, I’m blanking on the first part of your question, would you mind repeating it?

Brett Knoblauch: Yes. Just on maybe the cadence of which sites are — quicker to go?

Ben Gagnon: Yes. So really, that’s going to be driven by success on permitting time lines in the customers. So all three of the sites, Moses Lake, Sharon and Panther Creek are all actively in our go-to market right now. Every single one of those has customers engaged under NDA, and they have for quite some time. And so we’re continuing to push forward on those conversations and those negotiations. Really, I think what investors should think about with regards to permits, permits are more of a closing condition to a lease, right? They’re really not a starting condition to a negotiation. So we have these conversations and these negotiations simultaneously while we’re working towards permitting. As permitting gets closer and closer, the negotiations will also get closer and closer in tandem and the first site to get leased is likely to be the first site to be permitted.

Operator: Our next question comes from Stephen Glagola with KBW.

Stephen Glagola: Just on that last point, if you could clarify the sequencing here between like notice to proceed and lease execution. So in other words, like can you pre-sign leases contingent on notice to proceed? Or is like notice to proceed required before any major customer would commit to a lease?

Ben Gagnon: For a customer commit to binding in our view, they’re going to want NTP, and that’s based on the number of conversations that we are continuing to have and there probably are some customers who would be interested to sign prior to NTP, but those aren’t the investment-grade counterparties that we’re really seeking to engage with.

Stephen Glagola: Okay. And then just one more. How are you thinking about like Vera Rubin hardware availability in ’26 and like early ’27? And to what extent could that variability in supply influence the timing of lease discussions at your sites?

Ben Gagnon: Yes. That’s a good question, Stephen. We’ve been talking about Vera Rubin, I think, since Q3 call because all of our sites are basically coming online in 2027. So we’re trying to make sure that they are designed for the highest level of equipment that’s coming out in ’27 and ’28, which is the Vera Rubin. In terms of supply, we haven’t seen any impact so far. I understand there’s always geopolitical uncertainty in the world that may impact those supply chains. But given that energy is such a huge bottleneck, and it’s always been a huge bottleneck on the growth. I don’t think that there is going to be a geopolitical situation that’s going to make the bottleneck change from energy over to GPUs. So we don’t have any expectation right now that, that’s going to have any impact on leasing or demand for sites because power is still such an extreme bottleneck. It’s hard to imagine what’s going to overshadow that geopolitically.

Operator: Our next question comes from Michael Donovan with Compass Point.

Michael Donovan: Congrats on the progress. Can you provide an update on ESA progress, specifically Panther Creek’s ISA to ESA conversion?

Ben Gagnon: Yes. So that’s a great question, Mike. As investors probably know, we have 350 megawatts secured ESA with PPL. But in addition to that, we also have an ISA that enables us to draw down approximately 60 megawatts from the grid, and that’s associated with the existing transmission line and substation for the power plant that we currently have operating. In order to get that converted over, it’s really more of a regulatory matter. And so it’s hard to put an exact time line as to when those stamps are going to be received, but there’s no infrastructure that needs to be built. There’s no CapEx that needs to be spent. Really, it’s just a matter of getting the regulatory approval to convert a nonfirm service into a firm service, and that would enable us to increase our capacity beyond 350 megawatts to what we probably expect is going to be maybe 400 megawatts or possibly slightly more.

We expect this is going to happen this year, but it’s hard to put an exact time line on it, given it’s a regulatory matter.

Operator: Our next question comes from Brian Kinstlinger with AGP.

Brian Kinstlinger: Last quarter, Ben, you communicated, you expected the GPU as a service and Moses Lake site would be targeted for, I believe, the first quarter for go-live. How are you shifting to co-location change the timing if at all? And my second question is, can you talk about also how the global memory shortage is impacting your site development or changing your near-term needs or planning for lead times?

Ben Gagnon: Yes. So two parts to that question. In terms of switching from a GPU as a service to co-location just changing the business model doesn’t really impact the development time line. So we don’t really see any delay there associated with changing from GPU as a service, just to co-location. Really, it’s just a matter of how we want to allocate our capital and how we want to focus the business. When it comes to the memory shortage. As a pure-play infrastructure developer and owner that really is not coming into our calculus very much, mostly that’s a customer situation for them to resolve with their own supply chain because we’re not the ones investing in the GPUs and the compute and the servers.

Operator: Our next question comes from Martin Toner with ATB Cormark Capital Markets.

Martin Toner: Good morning. Can you guys elaborate or [indiscernible] can you kind of give us some time line thoughts there?

Ben Gagnon: So I’m going to repeat the question because it was a little quiet, just in case nobody else or other people had difficulty hearing. I believe the question was, can you give some time lines as to how we might be able to expand Panther Creek to 500 megawatts and beyond? So in order for us to move beyond the 350-megawatt ESA that we have secured, there’s really two sources for expansion. The first is converting over that ISA from non-firm service to firm service that I just spoke to a minute ago. And that’s really a regulatory matter that we expect to be resolved sometime this year. It could be tomorrow, it could be a few months from now. And then when it comes to expanding beyond that, what we have to do with that is we have to actually have new power applications.

The good thing here is that the utilities are actually looking to invest in new generation in the area. So in this particular instance, and we weren’t actually applying for new power. We actually have the utility call us and ask us how much more power we could take on site. Given the bottleneck constraint on power, that was obviously a very welcome call over here at Bitfarms to receive. And it’s a pretty unusual one in the industry, but they’re looking to scale up generation capacity in the area, specifically to service our site at greater capacity. So this is probably going to be 2 to 3 years time line because there’s a lot of process involved with spinning up new generation and building those new transmission lines. But for a lot of our customers, what they really want is the fastest pathway to energization and a clear path to scale over multiple years.

And so this really lines up with what the hyperscalers and what the neoclouds are searching for.

Martin Toner: That’s great. Hopefully, you can hear me better. Can you clarify when you expect to sign your first lease?

Ben Gagnon: So I can’t get into a specific time line. But in terms of milestones, as I spoke to earlier, it’s really about clearing NTP as kind of the last closing condition or last milestone for us to sign a lease. So I think for the investors and the analysts on the call, the important thing to keep track of, especially over the next coming months is the continued progress that we have towards NTP because once NTP is clear, that’s basically the last thing standing between us and a signed agreement.

Martin Toner: Got it. Great. And last one from me. Can you talk a little bit about why mining exahash in Q4 was at the level that it was at?

Ben Gagnon: So we continue to scale back our mining exposure as we continue to focus on our U.S. HPC infrastructure investments. So we haven’t made any investments into Bitcoin mining. We’re not spending any money on upgrades or new miners, and we’re actively working to scale down the fleet and actively working to spin off assets like we have in Paraguay that are not suitable for conversion. So investors should continue to expect our hash rate to continue to trickle down over 2026 as we continue to execute on this transition to HPC and AI.

Operator: Our next question comes from Mike Colonnese with H.C. Wainwright & Company.

Michael Colonnese: So, Ben, I’m just curious, after securing the remaining permits across the three sites, which sounds like likely to take place in the coming months here, what does the time line look like from a data center construction and delivery standpoint? It sounds like you’re pretty optimistic that revenue generation could commence as soon as next year, but any additional color there would be helpful.

Ben Gagnon: Yes. I mean, really, this is the year of execution in 2027 is the year of delivery. And so at all three of our projects that we talked about today, Panther Creek, Sharon and Washington, we all expect them to come online and start delivering megawatts and start generating revenue to customers in 2027. We’ll continue to provide updates as we go along. And I think once we have cleared NTP and we have signed leases, there’s going to be a lot clear visibility that we can provide to investors for each specific project and their specific time lines.

Michael Colonnese: Got it. And then back to Bitcoin mining operations, it sounds like you’re progressively going to be scaling back hash rate as you bring some of the HPC AI data centers online. I guess what’s the best way to think about hash coming offline and kind of flowing through your operating results over the near term here?

Ben Gagnon: I’ll speak to it at a high level and then maybe I’ll pass it off to Jonathan for some further clarity. But right now, the Bitcoin mining remains profitable, but it’s not it’s not very — it’s marginal. So it’s still contributing to the business. But really, it’s not the focus of the business. It’s not where we’re investing our time, it’s not where we’re investing our efforts. And given that we have been so successful last year in raising capital and strengthening our balance sheet. It’s really not super impactful for the developments that we have this year, the operations or the CapEx. So we’ll just continue to scale that down, trying to maximize value in the disciplined exit. If it makes more sense to maybe sell some miners a little bit earlier then we might need to in order to begin instruction, we’ll evaluate that as we will always do to maximize value for our shareholders.

But really, we kind of see this as a pretty minor element of our balance sheet and a minor element of the financial plan for this year. Jonathan, do you want to add anything further?

Jonathan Mir: Only that when we think about our liquidity going forward, the strategic objective is to ensure we are well capitalized through the lease process and beyond without the need to raise any new capital in the markets and that takes into account the current state of Bitcoin mining operations. It’s not assuming any improvement in the economics there. So our plan is built on conservative assumptions around the status of the Bitcoin market.

Operator: Our next question comes from Nick Giles with B. Riley Securities.

Nick Giles: Good morning, Keel team. In the interim period where Bitcoin mining operations are wound down, but kind of pre-revenue generation on the HPC side, could the generating assets at Panther Creek and Scrubgrass be utilized in any way such as the PJM capacity auction?

Ben Gagnon: So those power plants do actually participate in PJM capacity auctions. We’ve done that for quite some time. And so we do benefit from the capacity payments that we received there.

Nick Giles: Got it. Okay. And any order of magnitude of what those could be kind of in the 2026 planning year?

Ben Gagnon: So I mean, really, it’s — we’ve kind of maxed out on the capacity auction payments. They set a ceiling, and that’s where the capacity auction payments closed.

Nick Giles: Got it. Understood. Maybe one for Jonathan. You’ve made some progress on the capital structure, but just was hoping for any additional comments you might have on what you’re looking for in an initial debt package, how you’re seeing term shift and kind of what tools you have at your disposal during construction and kind of post energization.

Jonathan Mir: Good question. Thanks, Nick. So our basic approach is to compare and contrast our financing options down at the asset level and upstairs at the parent level. And certainly, one of the things that we’ve seen in the market that has caught our attention like everyone else, is the tightening of spreads between folks issuing high-yield debt in the market that would seem like quite attractive levels for strong investment-grade counterparties or credit wraps. And those converging towards the levels seen in bank-originated classic construction of project financing. So we’ll be — each of those has its own advantages in terms of simplicity of managing the actual capital once it’s raised versus negative carry costs. And as we get closer to a funding point, we’ll make the decision as to what seems best for our shareholders in terms of how we decide to finance.

I’m sorry, Nick, I was just going to say that the markets for our space and for infrastructure generally seem calm right now.

Operator: Our next question comes from Brian Dobson with Clear Street.

Gregory Pendy: It’s Greg Pendy in for Brian Dobson. Just I guess one final one. Just I guess, one final one. Just on the redomiciling to the U.S., are there any implications to costs or structural implications in terms of ownership that we should be aware of as you enter this over the next couple of days?

Ben Gagnon: One of the benefits and reasons for the redom is that we will now be eligible for inclusion in indices that require — want to be a U.S. domiciled company. So for example, we’ll be eligible for inclusion in the Russell 1000 and the Russell 3000 as well as for ownership in any other fund who was otherwise limited to the purchase of U.S. securities. We view that as being quite helpful in terms of moving our shareholder base to one that is institutional and long term. There are no other — there are no cost or flexibility implications in our end. We simply see this as a nice path forward with a lot of benefits for our shareholders.

Operator: Our next question comes from Bill Papanastasiou with Chardan Capital Markets.

Bill Papanastasiou: Just wanted to touch on the Washington side and decision to shift towards colo. Can you confirm that this won’t have any material impact on the purchase commitment that was entered into November? Or is the team considering the shift in development allocation to other sites?

Ben Gagnon: Thanks, Bill. No impact on the capital commitments and the equipment we’ve already purchased for the Washington site by changing business models. In fact, actually, it just helps to reduce the CapEx because we’re no longer paying for the compute.

Bill Papanastasiou: Understood. And then how should we generally be thinking about maintenance CapEx on existing Bitcoin mining sites as you gradually shift over to AI HPC here?

Ben Gagnon: We’re not making any investments into the Bitcoin mining sites. Basically, we’re just continuing to keep them up and running. And so no further investments are being made in the sites into new sites or into new miners.

Operator: Thank you. This concludes the question-and-answer session. I’d like to turn the call back over to Ben Gagnon for closing remarks.

Ben Gagnon: Thank you very much, everyone, for joining our call today and really look forward to speaking to you next time as Keel Infrastructure. Have a great day.

Operator: Thank you for your participation. This does conclude the program. You may now disconnect.